Stage 4: Contract Administration

This is the practical stage of building where once again your Architect will prove to be very useful.

It can be extremely difficult to locate a builder whose workmanship you are happy with, and who is pleasant to work with.

You may be fortunate to know a builder who did a good job for friends.Otherwise, your Architect can normally suggest a number of builders whose work is generally of a good standard. Your Architect's suggestion in such cases is invaluable, because when a competent builder is on the job, you can be far more confident that the work will be carried out in a professional manner.

The Contract

Once you have chosen a builder your Architect can help the selection and preparation of a contract from the many Standard forms available. It is strongly recommended that you select a contract recognised by the Royal Australian Institute of Architects (RAIA).  Many other types of contracts are heavily loaded in the builders favour. A good contract will ensure that appropriate methods of dispute resolution are open to you it is also important to make sure that the contract defines the responsibility of your Architect in the building process.

Then you can sit down with the builder and your Architect to sign the contract documents.

Starting On Site

If you are renovating, be prepared for that quaint little laundry to be irreverently torn apart, that worn-out sink and hot water service to be thrown on to the back of a truck and that dutiful 1950's pink loo to be split asunder.

Holes will be dug and mounds of earth will appear and your once-settled site will resemble a war zone.

Be patient and set aside time for regular contact with your Architect and builder to discuss the progress of the works, any decisions that have to be made and any changes or improvements to be effected.

It is with this regular monitoring that the Architect can establish whether or not the builder is on schedule, and whether he is entitled to time extensions.

Progress Payments

Most building contracts make provision for the builder to be paid progressively throughout the construction works. In some states this is required by law. The builder submits his claims to your Architect.

Your Architect will assess progress of the work against the builders claims, and advise you on the amount of the payment to be made. It is most important that you only pay for the value of the work done and materials on site.

Variations

By thoroughly defining what is to be done, your Architect has avoided many areas of confusion which normally lead to variations. However a few may still exist. A "variation" is any deviation from the original contract.

Some unethical builders give low tender prices in the hope a recouping their costs by claiming many variations.

When variations arise, your Architect will mediate between you and the builder, to reduce the possibility of on-site friction.

This is another area where your Architect can save you money by negotiating an equitable variation amount, if any is reasonable.

If you have contracted direct with a design-and-construct company, their interest will naturally be in interpreting the construction document's details in favour of the builder (since they are one and the same person). Many people find it hard to be emotionally detached during the ensuing negotiations between themselves and the building company because their home is such a core part of their lives.

Completion

Your Architect protects your interests during the final stages, by issuing a "Notice of Practical Completion". This notice defines the date from which the building is handed over to you for your use. It also defines the beginning d the "defects liability period", during which an amount of money is retained by you to provide safeguards against defects arising after the building work is completed.

Practical completion also defines the date a cessation of the builder's responsibility for insurance of the works.

Defects Liability Period

During a period after the work is completed, the builder will remain liable under the terms of the contract to remedy any defect in workmanship and materials that may become apparent. Your Architect will assist by noting these defects at the "Practical Completion Inspection", which may take many hours.

Your Architect will note jamming doors or windows, structural cracks in concrete and plasterwork, tiles loose on walls, gutters incorrectly levelled, and many other irritating items. He or she may discover faults not noticeable to you. This is another area where an Architect is useful in protecting your interests.At the end of the defects liability period, your Architect will issue a "Final Certificate", which indicates that the works under the contract have been completed.This is usually the stage at which your Architect's services will be complete. Don't be surprised, however, if your Architect is keen to stay in contact, to make sure that your project has been a long-term success for you.



© Copyright 1997 Archicentre Limited & Green Webb Pty Ltd
All Rights Reserved. - ACN: 001 866 520 & 074 426 207
Media Office:  P.O. Box 2412, Kew, Victoria 3101, Australia
Tel: +61 3 9818 5700 Fax: +61 3 9818 5044

Disclaimer